The £70 million project comprises both landside and airside terminal expansion and refurbishment works. The terminal expansion and reconfiguration will increase the floor space by approximately 25% and create a more integrated and ergonomic building which will bring into use areas that were redundant.

The works included:

  • The construction of an infill building.
  • A new two storey pier (Pier B) and associated link building.
  • Construction of infills to existing Pier A.
  • Extension and relocation of the Immigration Hall.
  • Reconfiguration of duty-free area.
  • Refurbishment and extension of domestic and international arrivals.
  • Relocation and extension of passenger screening area.

ChandlerKBS provided full pre and post contract cost management services.